dc.description.abstract | PT. Campina is a company that produces ice cream, where variations of the
product on the company's lot. Currently the production process at the company
often have production time inaccuracy, caused by delays in the procurement of raw
materials. to reduce these inaccuracies will be done using the raw material planning
analysis method of Economic Order Quantity. In these methods is capable of
finding the value of safety stock and reorder point is useful for companies that have
not been implemented.
Data collection techniques are performed directly from the company. From
the data obtained by calculation is performed to locate the required value in the
research. The formula used in the calculation of such value EOQ (economic order
quantity), total cost, safety stock, reorder point and. From the results of research
that can be proved using the methods of EOQ company can do savings in the
procurement of raw materials/packing of 45%-52%. | en_US |